Crooble Road Level Crossing upgrade

From 1 April 2022, our contractor Trans4m Rail will continue level crossing and drainage upgrade works on Crooble Road.

Snapshot

Date

April 2022 - June 2022

Working hours

7am to 6pm, seven days a week

Location

Crooble Road

Town
  • Crooble
Local Government Area
  • Gwydir Shire

Work being done

Works will include installing new drainage structures and signals to complete the level crossing upgrade.

Works are permitted to occur on Sunday under the relevant project approvals.

To facilitate the works, a temporary road has been constructed to divert traffic around the existing level crossing. The temporary gravel access road will accommodate road trains.

What can I expect

  • Trucks and other vehicles entering and exiting the construction site
  • Construction machinery and equipment operating on site
  • Delivery of materials and equipment
  • Some of these works will be noisy and mitigation measures will be in place
  • Temporary traffic delays are expected during work hours.

Machinery used

  • Trucks,
  • cranes,
  • graders,
  • excavators,
  • loaders,
  • rollers and
  • water/vacuum excavation trucks

will be used within the construction impact zone.

How we’re managing impacts

  • Traffic control will be in place, where required
  • Water carts will be on site to wet down areas to assist in managing dust.

Contact

Phone: 1800 732 761

Email: inlandrailnsw@artc.com.au

Post: Inland Rail, GPO Box 14, Sydney NSW 2001


Share: