Works and planning

The Gowrie to Helidon section of Inland Rail will be built predominantly within the existing rail corridor and the Department of Transport and Main Roads’ Gowrie to Grandchester protected rail corridor. A study area was identified and refinements considered as part of the reference design process.

Work is expected to include building:

  • 28km of new dual gauge track
  • a 6.2km long tunnel (approximately)
  • 13 bridge and viaduct structures (6.7km in total length)
  • three crossing loops

Current and upcoming field investigations

Last updated 22 December 2022.

Location/sType of workTimingContractorWhat to expect
Gowrie to KagaruGroundwater monitoringOngoingGoldersContractors checking groundwater monitoring bores on public and private properties.
Gowrie to KagaruSurface water monitoringOngoingGoldersContractors collecting water quality data from waterways relevant to the projects, generally in line with the monitoring sites outlined in the draft EIS’s.
Gowrie to KagaruCadastral SurveyOngoingRPS SurveysInstallation and establishment of major survey control marks within the G2K project areas.
Gowrie to HelidonGround Water samplingDecember 2022 to January 2023Regionerate Rail
(Epic Environmental and Webuild)
Installation and monitoring of ground water monitoring bore on and private properties.
Gowrie to Helidon and Helidon to CalvertSoil samplingMarch to May 2023FFJV (Aurecon) Contractor conducting soil sampling on properties located on and near the alignment, as agreed.

Watch a fly-through of the project

Get a birds-eye view of the Gowrie to Helidon project. This video shows the alignment as of August 2019. The fly-through video is for illustration purposes and for discussion and community consultation.

Visualisations

To get a sense of what your community will look like after the project has been completed, check out our visualisations of the proposed design.

Visualisations are for illustrative purposes and not to scale.

Toowoomba Range tunnel

This visualisation provides a three-dimensional view of the Inland Rail Gowrie to Helidon project’s indicative Toowoomba tunnel reference design. The visualisation demonstrates the approach to tunnel safety and ventilation, including the safety provisions within the tunnel, water tanks, pump buildings, backup generator, transformer yard, access roads, tunnel portal, ventilation shaft and ventilation buildings.

This 3D visualisation is for illustration and discussion purposes only. The final design of the tunnel will be prepared at the detailed design stage.

Six Mile Creek viaduct

This visualisation provides a three-dimensional view of the project’s Six Mile Creek viaduct reference design. This viaduct is the highest of the 13 bridge and viaduct structures that we expect to build for the project. It stands approximately 50 metres tall at its highest point at Six Mile Creek—about the same height by which the Sydney Harbour Bridge clears the water.

The Six Mile Creek viaduct is also the second longest viaduct on the project, spanning 966 metres as it passes over the Toowoomba Bypass, Six Mile Creek, Gittins Road and generally mountainous terrain. The structure accommodates a single line running, at 80km/h.

This 3D visualisation is for illustration and discussion purposes only. The final design of the structure will be prepared at the detailed design stage.

Junction Street, Gowrie Junction

Junction Street, Gowrie Junction, Queensland, showing current view Junction Street, Gowrie Junction, Queensland, view showing proposed design

Burnview Avenue, Cranley

Burnview Avenue, Cranley Queensland, showing current view Burnview Avenue, Cranley Queensland, showing view with proposed design

Katoomba Point Lookout, Prince Henry Heights

Katoomba Point Lookout, Prince Henry Heights, Queensland, current view Katoomba Point Lookout, Prince Henry Heights, Queensland, view showing proposed design

Murphys Creek Road, Postmans Ridge

Murphys Creek Road, Postmans Ridge, Queensland, showing current view Murphys Creek Road, Postmans Ridge, Queensland, showing view with proposed design

Learn about the major aspects of the Gowrie to Helidon project

Get an overview of the G2H alignment selection, utilising existing and gazetted rail corridors

Find out how our proposed replacement of the Gowrie Junction level crossing with a road over rail bridge will provide a safer outcome for the nearby communities.

Learn about our approaches to safety and tunnel ventilation, aspects that informed the current design thinking for ventilation and tunnel portals, and watch a 3-D visualisation of the proposed tunnel reference design.

Discover how we propose to deliver a fast and safe alignment down to the Lockyer Valley floor using viaduct structures and providing safe road/rail interfaces.