November 4, 2020
No. 104: Final maintenance/construction works
In the coming months we will be completing the final maintenance/construction works from Parkes to Narromine.
- October 2020 - January 2022
- Between Parkes and Narromine
- Parkes, NSW, Narromine, NSW
September 8, 2020
No. 103: Commissioning of the Parkes to Narromine railway line
The commissioning of the railway line requires testing of the rail signals near level crossings and inside signalling huts, over eleven days and nights.
- April 2024
September 1, 2020
No. 102: Bogan Road single lane extended
As part of these works, we have been upgrading the level crossing at Bogan Road, Goonumbla. Due to continued wet weather, opening Bogan Road back to two-way has been delayed. We apologise for any inconvenience.
- April 2024
September 1, 2020
No. 101: Road work temporary closure – Coradgery Road, Peak Hill
We are completing final pavement work on Coradgery Road on either side of the level crossing, and Station Lane. Local access will be maintained into Station Lane during the pavement works.
- April 2024
July 3, 2020
No. 100: Level crossing upgrades and temporary closures – Wyatts Lane, Parkes
We are upgrading level crossings as part of building Inland Rail between Parkes and Narromine. While we do this, we need to temporarily close public roads.
- April 2024
June 3, 2020
No. 99: Level crossing upgrades and temporary closures – Tinks Lane, Tomingley
We are upgrading level crossings as part of building Inland Rail between Parkes and Narromine. While we do this, we need to temporarily close public roads.
- April 2024
June 3, 2020
No. 98: Bogan Road temporary diversion construction
We are upgrading level crossings as part of building Inland Rail between Parkes and Narromine. While we do this, we need to temporarily close public roads.
- April 2024
June 3, 2020
No. 97: Fairview Siding Road, Narromine extended closure
We are upgrading level crossings as part of building Inland Rail between Parkes and Narromine. While we do this, we need to temporarily close public roads.
- April 2024
May 3, 2020
No. 96: Bogan Road temporary diversion construction
We are upgrading level crossings as part of building Inland Rail between Parkes and Narromine. While we do this, we need to temporarily close public roads.
- April 2024
May 3, 2020
No. 95: Level crossing upgrades and temporary closures – Henry Parkes Way level crossing completed
We are upgrading level crossings as part of building Inland Rail between Parkes and Narromine. While we do this, we need to temporarily close public roads.
- April 2024