Info hub

Explore information about the Victorian section of Inland Rail, from Beveridge to Albury.


April 22, 2024

Powerline works, North East rail line, Benalla, 28 April 2024

To enable the safe running of double-stacked freight trains additional height clearance between the rail and powerlines is required in some locations along the North East rail line near Lowens Lane, Benalla.

  • 28 April 2024 - 28 April 2024
  • Benalla
  • Benalla
Notification

April 22, 2024

Wangaratta Station electrical works, 27 Apr-3 May, 2024

McConnell Dowell will conduct electrical works at Wangaratta Railway Station along a section of Cusack, Spearing and Norton streets between Saturday 27 April and Friday 3 May.

  • 27 April 2024 - 03 May 2024
  • Wangaratta Station precinct
  • Wangaratta
Notification

April 22, 2024

Seymour-Avenel Road bridge works May 2024

Inland Rail will continue construction works in and around the Seymour-Avenel Road bridge in Seymour during May.

  • May 2024 - May 2024
  • Seymour-Avenel Road
  • Seymour
Notification

April 12, 2024

Early works to start for next stage of Inland Rail in Victoria

John Holland will deliver early commencement works and early delivery activities for the remaining eight Inland Rail sites in Victoria.

April 12, 2024

Beveridge to Albury Tranche 1 community benefits snapshot

Infographic summarising benefits of the Beveridge to Albury project for the local community from October 2022 to February 2024.

March 25, 2024

Wangaratta Railway Station and Green St bridge works (including night works) April 2024

Inland Rail will continue construction in and around Wangaratta Railway Station and Green Street bridge during April.

  • April 2024 - April 2024
  • Wangaratta Station precinct
  • Wangaratta
Notification

March 25, 2024

Beaconsfield Parade bridge works, Glenrowan: April 2024

Inland Rail will install streetlighting, pedestrian handrails and anti-throw screens on the new Beaconsfield Parade bridge during April.

  • April 2024 - April 2024
  • Beaconsfield Parade bridge
  • Glenrowan
Notification

March 25, 2024

Seymour-Avenel Road bridge works April 2024

Inland Rail will continue construction works in and around the Seymour-Avenel Road bridge in Seymour during April.

  • April 2024 - April 2024
  • Seymour-Avenel Road
  • Seymour
Notification

March 15, 2024

Major track possession works completed

The Australian Rail Track Corporation Inland Rail has now completed the largest ever scope of works undertaken during a single track possession in Victoria.

March 4, 2024

Inland Rail surges ahead with March construction blitz

The Inland Rail project will surge forward in March with the completion of a massive schedule of construction work along the North-East rail line.

More Resources