North Camurra to Crooble major track upgrade works

Our contractor Trans4m Rail will start operating on-track machines (rolling stock) between between North Camurra and Crooble as part of ongoing track construction works from Friday 4 March 2022.

Snapshot

Date

04 March 2022 - March 2022

Working hours

7am to 6pm, seven days a week

Location

North Camurra and Crooble

Town
  • North Camurra
  • Crooble
Local Government Area
  • Moree Plains Shire

Work being done

Works will generally occur between 7am and 6pm Monday to Sunday. Low impact activities such as machinery re-fueling, managing environmental controls and traffic control may also occur outside of these hours. Residents will be notified in advance of any out-of-hours work.

Residents should be aware that on-track machines, including the ballast train, will be active during these works. Please follow all traffic control signage at level crossings.

Works will involve:

  • Installing concrete sleepers and new steel rail
  • Flash butt welding of rail
  • Installation of ballast
  • Tamping the track to compact the ballast, sleepers and rail
  • Reinstating traffic control and signage at level crossings.

What can I expect

  • Rolling stock operating on the rail lines
  • Trucks and other vehicles entering and exiting the construction site via access gates
  • Changed traffic conditions at level crossings
  • Construction machinery and equipment operating on site
  • Delivery of materials and equipment
  • Motorists should follow traffic controls and drive with caution.

Machinery used

  • Hi-rail vehicles (rolling stock)
  • trucks
  • excavators
  • loaders
  • rollers
  • watercarts will be used within the construction area.

How we’re managing impacts

  • Traffic control and signage will be in place, where required
  • Water carts will be on site to wet down areas to assist in managing dust.