All news

July 29, 2022
Narrabri to North Star Phase 2 project update July 2022
This month, we’ve been finalising technical documents to support the project’s Environment Statement (EIS), particularly addressing hydrology feedback from the Department of Planning and Environment (DPE).

July 28, 2022
Securing access for emergency vehicles in Moree
We acutely understand the Moree community’s expectation for unimpeded 24/7 access for emergency vehicles across both sides of the Inland Rail alignment once freight trains are operating.

July 28, 2022
Kids at Work Day enjoyed by everyone
There was a shift in gears on Tuesday 24 June at Inland Rail’s Brisbane office when we held our inaugural successful ‘Kids at Work Day’ event.

July 28, 2022
A bonus win for Moree Junior Rugby Club
Big smiles and even bigger tackles are being seen on the footy grounds in Moree after the Junior Rugby Club received grant funding through the Inland Rail Community Sponsorships and Donations program.

July 28, 2022
A big month for Inland Rail crew and the Moree community
Our construction contractor, Trans4m Rail, supports team members not just when they’re on the job but also when it comes to the things that matter to them and the community in which they work. In July, Trans4m workers attended NAIDOC Week events alongside members of the Moree community, while a group of smiling graduates were recognised for taking the next step in their careers.

July 28, 2022
Hi-rail vehicles 101
While there are activities that are similar on all construction jobs, not all equipment used is the same. When it comes to building, or maintaining, a railway, we use specialised construction vehicles that can travel on and off the tracks to perform a variety of tasks.

July 28, 2022
Narrabri to North Star Phase 1 project update July 2022
In July, our contractor Trans4m Rail progressed earthworks between Narrabri and Bellata, with 100% of the existing topsoil now stripped and stockpiled ready for re-use and backfilling of the new track formation well underway. Meanwhile, our signalling team installed two signalling huts at the Waterloo passing loop.

July 25, 2022
ARTC releases preliminary designs for Inland Rail in Glenrowan
The Australian Rail Track Corporation (ARTC) has unveiled updated designs for the Inland Rail project in Glenrowan to the local community.

July 22, 2022
Biodiversity offsets team successfully retires Parkes to Narromine credits
In July, the NSW Biodiversity Offsets team ticked off its first major milestone by retiring all 4,606 biodiversity credits for the Parkes to Narromine (P2N) section in New South Wales.

July 21, 2022
Female participation is more than just numbers for our Vic contractor McConnell Dowell
ARTC Inland Rail recognises the importance of a diverse workforce and we are proud of our strong female representation, particularly across leadership roles.